Brattleboro Reformer
February 27, 2007
By Bob Audette
BRATTLEBORO -- The last argument against Vermont Yankee's
extended power boost was dismissed by the Atomic Safety and
Licensing Board Monday.
The New England Coalition had originally started with seven
arguments -- or contentions -- about why it felt the power
uprate for the nuclear power plant in Vernon should not be
approved.
That list had been winnowed down to the one contention which the
board dismissed.
Entergy applied for the uprate in 2004. It was approved March
2006. In May of last year, the plant reached its new power level
of 120 percent, from 1,593 megawatts to 1,912 megawatts.
The coalition had contended that the "uprate" should not be
granted unless "large transient testing" was conducted.
Those tests are intended to show that the plant will operate "in
accordance with design specifications both during normal steady
state conditions and ... during and following anticipated
operational occurrences, such as main steam isolation valve
closures and a generator load rejection," according to the
decision released Monday.
"We have said our uprate was grounded in NRC regulations," said
Rob Williams, spokesman for the power plant, which is owned by
Entergy.
Williams said the plant's "power ascension testing," was done
"consistent with our conservative operating philosophy. The NEC
was clearly wrong in its interpretation of NRC regulations
regulating power ascension testing and the ASLB upheld that
view."
Though the group had a right to bring its concerns to the
board, he said, "this resolves the issue and our focus is on
operating the plant safely and reliably."
A spokesman for the watchdog group said he was not surprised by
the decision.
"Entergy spent millions of dollars deflecting our safety
concerns and employed a 900-attorney international law firm to
oppose us," wrote Ray Shadis, in a press release. In addition,
he wrote, "NRC's legal staff of 60 attorneys always weighs in
against the public interest groups no matter if the licensee's
application is complete or incomplete."
The coalition argued that Entergy had not shown why it should be
exempted from the requirement to test safety systems in a
full-scale test in the event of electrical failure leading to
generator load rejection or rapid closure of the plant's main
steam isolation valves, said Shadis.
In a valve closure situation, the safety valves, which prevent
fission products from the reactor from being released into the
steam system outside of the reactor, close down, forcing an
emergency shutdown, or SCRAM.
A valve transient test is used to determine "how the reactor,
reactor control system and steam system will perform in the
event of an MSIV transient."
A generator load transient occurs when "the electrical output
from the nuclear power plant's generators suddenly has no place
to go."
But the ASLB ruled that industry experience with boiling water
reactors similar to those at Yankee, as well as the operating
record of the nuclear power plant, precluded the need to conduct
the tests requested by the coalition.
In its decision the board wrote that the "operating experience
at VYNPS," modifications made as part of the uprate process and
component testing "all indicate that the EPU will not introduce
new thermal or hydraulic phenomena that warrant conducting ...
transient tests."
"The ultimate factual and legal issue in this case may be
summarized as whether ... Entergy has adequately demonstrated
that the VYNPS structures, systems and components will perform
satisfactorily under uprated conditions" without the tests,
wrote the board in its decision. "Entergy and (NRC) staff
provided ample evidence that the industry operating experience
at analogous boiling water reactor plants indicated that large
transient testing ... is not needed."
Entergy argued that the tests weren't necessary, said Neil
Sheehan, spokesman for the Nuclear Regulatory Commission. The
ASLB "agreed that based on industry experience and based on
information received through this process, Entergy was able to
demonstrate they could safely shut down this reactor without
doing large transient testing."
New England Coalition has 15 days in which to appeal the board's
decision to the NRC commission. However, said Diana Sidebotham,
the group's president, "we have limited resources and right now
we are building a legal fund to represent the public's interests
in the license renewal case, currently before a similar Atomic
Safety and Licensing Board."
Despite the ruling, Shadis said he was proud of the work the
coalition had done to force Entergy to look more closely at its
safety systems.
"I am satisfied that we made the entire proposition of uprate
just a little less dangerous," he said, forcing Entergy and the
NRC "to look at safety and engineering issues in depth and
detail that they never anticipated."
At each stage, every element in the process was checked, rechecked and then checked again before continuing toward the goal of raising Vermont Yankee's capacity from 540 MW to 650 MW. The standards employed by Entergy not only met the stringent safety standards required by the NRC- it exceeded them.
Vermont Yankee was designed with multiple and redundant safety systems and is equipped with industry-leading safety measures to prevent incident. The plant's features include housing the nuclear reactor in leak tight containment domes that are several-feet-thick, steel-reinforced concrete lined with a stainless-steel inner shell.